In Situ Remediation in North Carolina


By Tracey Tapley, PG, M.SAME

An in-situ remediation strategy employed at a pair of Formerly Used Defense Sites in North Carolina helped achieve No Further Action status following years of stalled progress. 
Innovative in situ remediation technologies can help accelerate groundwater cleanup at legacy defense sites like NAAS Manteo in North Carolina, reducing long-term petroleum contamination.

In 1986, an influential program was established that would be responsible for addressing legacy contamination at over 9,000 properties once operated by the Department of Defense: Formerly Used Defense Sites (FUDS).

Today, nearly 40 years later, cleanup has been completed at over 3,800 locations. Many of the sites supported fuel storage, distribution, and training during World War II and the Cold War; these past actions left behind petroleum hydrocarbons in soil and groundwater that can persist for decades.

The U.S. Army Corps of Engineers (USACE), the agency responsible for conducting remediation work through FUDS, is tasked with finding approaches that can quickly and effectively meet typically stringent cleanup goals to achieve regulatory closure and support beneficial reuse of the properties.
In North Carolina, two cleanup sites—Naval Auxiliary Air Station (NAAS) Edenton and NAAS Manteo—demonstrate the positive benefits of using a strategic in situ remediation approach.

Initial cleanup efforts in the mid-1990s included the removal of 10 aboveground storage tanks, three underground tanks, and associated pipelines, along with the excavation of more than 7,500-T of contaminated soil.

Longstanding Issues

Despite over-excavation of impacted soils and over a decade of monitored natural attenuation, residual contamination at Manteo and Edenton exceeded North Carolina’s Groundwater Quality Standards. To remediate the petroleum plumes at both sites, USACE implemented injections of colloidal activated carbon (CAC).

NAAS Manteo. In 2007, a release related to previous military operations at former NAAS Manteo was discovered. This prompted the removal of six underground storage tanks, 455-T of impacted soil, and 300-T of sludge. Then in 2011, an additional 1,366-T of contaminated soil was excavated. While these actions reduced contaminant mass, groundwater monitoring revealed persistent benzene, isopropylbenzene, and total petroleum hydrocarbons. After more than 10 years of monitored natural attenuation, contaminant concentrations plateaued.

To accelerate site closure, in 2020, USACE and its industry partners injected approximately 23,300-gal of PetroFix (a water-based remediation fluid developed by Regenesis) into two residual plume areas encompassing more than 3,000-ft², using 68 hydraulic percussion-driven injection points. The injection interval spanned from 3-ft to 12-ft below ground surface, targeting the shallow aquifer zone most impacted by the release. Visual confirmation of PetroFix distribution directly into soil cores allowed the field team to adjust injection tooling and pressures to optimize coverage.

In 2021, the treatment area was expanded slightly after a monitoring well just outside the initial grid continued to show elevated concentrations. Following the supplemental application, groundwater sampling over four straight quarters demonstrated that all contaminants of concern were below regulatory limits, including benzene at 1-ppb. By 2023, the North Carolina Department of Environmental Quality issued a No Further Action. This determination brought closure to a petroleum release case that had remained open for over 15 years.

NAAS Edenton. When NAAS Edenton was decommissioned in 1958, responsibility for the property was transferred to local entities—but a legacy of petroleum contamination remained. Initial cleanup efforts in the mid-1990s included the removal of 10 aboveground storage tanks, three underground tanks, and associated pipelines, along with the excavation of more than 7,500-T of contaminated soil. While this work removed much of the source mass, groundwater monitoring revealed persistent impacts from benzene, naphthalene, and related hydrocarbons—exceeding groundwater quality standards.

In 2020, PetroFix injections were conducted across two target areas covering roughly 3,000-ft², using 33 direct-push injection points. During application, the field crew encountered “daylighting” at several locations near a monitoring well. This limited the distribution of the treatment solution in that area of the plume. Due to the daylighting, the injection plan was revised and a supplemental injection event was completed in 2021 that expanded the treatment area by 1,000-ft².

Following the injections, quarterly groundwater monitoring demonstrated all contaminants of concern had been reduced below stringent cleanup goals—benzene concentrations were sustained below 1-ppb for over 18 months.

In recognition of these results, the North Carolina Department of Environmental Quality issued a determination of No Further Action, successfully closing a site that had been in monitored natural attenuation for over 20 years.

Accelerating Cleanup

The successful remediation of NAAS Manteo and NAAS Edenton underscores the value of integrating innovative, resilient in situ technologies into the FUDS program. Across the country, many petroleum release sites share a similar trajectory: tanks and contaminated soils are removed, monitored natural attenuation is utilized, and yet residual plumes linger for years.

By applying a colloidal activated carbon formulation, USACE demonstrated a pathway to accelerate closure timelines while containing costs. The dual action of sorption and enhanced biodegradation provided immediate risk reduction and sustained treatment while meeting stringent groundwater standards. Importantly, both sites achieved No Further Action determinations following relatively modest injections.

The FUDS program will continue to face the challenge of addressing legacy petroleum contamination where conventional approaches have not delivered permanent effectiveness. More aggressive yet economical approaches are possible. The lessons learned in North Carolina offer a replicable system for projects nationwide—a model that emphasizes cost efficiency, long-term protectiveness, and returning properties to safe and productive use.

Tracey Tapley, PG, M.SAME, is Senior Geologist, Geology/Hydrogeology and HTRW Design Section, USACE Savannah District; tracey.tapley@usace.army.mil. 


The Military Engineer archives