Future-Proofing Defense Facilities: Construction Approaches for Evolving Operational Needs
By Adam Skwirsk, AIA, M.SAME
As military construction across the Defense Department continues to be driven by urgent schedules and constrained budgets, making intentional early design decisions around structure, systems, and delivery approach can help installations remain flexible and adaptable over the long term.

While pre-engineered buildings can be delivered quickly and reduce initial costs, conventional construction approaches often provide greater adaptability for long-term mission requirements.
U.S. Coast Guard photo.
Delivering architecture-engineering services to build defense facilities requires balancing accelerated timelines with long-term mission adaptability. Inherently, these projects are schedule-driven due to mission-ready requirements, which often demand expedited design and construction. While aligning with faster, more cost-effective approaches can meet immediate operational needs, they also may limit flexibility for future modifications that evolving warfighting missions require.
A critical early decision in the design process is the selection of building type. Pre-engineered buildings provide low-cost, rapid construction. They are difficult to modify, however, which can constrain future mission adaptability. In contrast, traditional stick-built structures require more time and resources upfront, but they offer a flexible framework that can evolve with changing operational requirements. These programming and design choices establish the foundation for how well a facility can respond to future mission demands, making them some of the most consequential decisions in any project.
Successful facility delivery hinges on choosing construction approaches that align with immediate operational needs and long-term adaptability. The right approach ensures that schedules, budget constraints, and operational objectives are balanced. By carefully considering these trade-offs, facilities can be delivered quickly to meet readiness requirements while remaining capable of adapting to the evolving demands of tomorrow.
- Decisions made during the programming and design process are paramount to the short-term and long-term success of a project. Spending time discussing what success looks like with a perspective that considers 10-year, 20-year, or even 30-year horizons is a vital step in planning.
- Discussions around flexibility, adaptability, and lifecycle performance also help position facilities to evolve with changing service needs, technologies, and user demands.
- Aligning stakeholders on operational goals, maintenance expectations, and expansion potential can reduce risk, minimize costly rework, and ultimately result in a more resilient and efficient built environment.

While pre-engineered buildings can be delivered quickly and reduce initial costs, conventional construction often provides greater adaptability for the long-term. Photos courtesy AECOM.
Short Term, Long Term
The building type and method of construction needs to be considered early in design, with the perspective of future flexibility and changing operational requirements in mind. Often times during the design phase, the systems and requirements are still being developed, which means the design team might not be aware of the full requirements until later on. Deciding between pre-engineered or conventional construction can determine if a building is adaptable for potential operational changes.
Pre-engineered buildings are highly efficient in their design and are typically conceived for the performance requirements provided, without consideration for any future modifications. While these buildings can be made more adaptable by designing modular extensions, this would not work for smaller footprints or limited sites. When using this method, construction can experience long delays due to the process of making modifications to the structure. These alterations could come from operational changes, systems updates, or unexpected design modifications.
Conventional buildings (“stick-built”) often are more adaptable and designed to have a longer life expectancy. When considering the future, these facilities can be modified more easily without the need for expansion. Design adjustments can be accomplished quickly with direct access to the structural designer. These buildings are more resilient to evolving program requirements and can be tailored to meet higher performance criteria, including structural robustness, security, and specialized loading conditions. This flexibility allows owners to extend the useful life of the facility while minimizing costly disruptions or limitations associated with standardized systems.
Cost, Speed, Adaptability
Balancing cost, speed, and adaptability is a fundamental consideration in facility planning. And the contrast between pre-engineered and conventional structural systems provides a clear illustration of tradeoffs.
Pre-engineered buildings are typically more economical during the design phase. They are based on performance requirements rather than fully customized solutions. This reduces engineering effort, minimizes material usage, and allows for more efficient fabrication and installation. As a result, construction costs are generally lower and schedules are shorter—particularly when the building geometry is simple and changes are limited.
These characteristics make pre-engineered systems well-suited for storage, warehouse, and smaller auxiliary facilities where speed and cost are primary drivers and long-term replacement value is relatively low.
A practical approach is to establish the “bones” of the building early while intentionally embedding flexibility in key areas for later on.
Conventional systems, by contrast, require a more robust design effort; often, that leads to higher upfront costs and longer duration to fully design and construct. However, this initial investment of time and money also can yield significant long-term benefits. Conventional buildings are inherently more adaptable. These buildings are better suited for modifications, expansions, and reconfigurations as mission needs evolve. They are typically designed with a longer life expectancy and can better accommodate complex program requirements or multiple operational functions. For larger, mission-critical facilities or those bearing a substantial capital investment, this flexibility can translate into reduced lifecycle costs and greater overall value.
Because each approach offers distinct advantages, it is critical to evaluate their differing factors early in the project lifecycle, ideally during the programming phase. Gaining alignment on budget, schedule, operational complexity, and future adaptability allows project teams to select the most appropriate structural approach. Thoughtful consideration at this stage and collaboration with owners helps mitigate costly redesigns, minimizes risk, and ensures facilities can effectively support both immediate needs and long-term objectives.

Early programming and design decisions often determine how effectively a military facility can accommodate operational changes and mission growth over time.
Embedding Flexibility
Construction methodologies play a significant role in shaping a facility’s long-term performance, particularly when balancing speed with future flexibility. While fast-track delivery and phased construction packages can support aggressive schedules, they also lock in critical early decisions.
When foundational elements like structural systems, floor-to-floor heights, shafts, and primary utility corridors are planned with foresight, they create a framework that can accommodate changes over time.
Conversely, if early packages are optimized solely for the initial use, the building can quickly become rigid; this limits its ability to evolve as operational needs shift.
A practical approach is to establish the “bones” of the building early while intentionally embedding flexibility in key areas for later on.
A practical approach is to establish the “bones” of the building early while intentionally embedding flexibility in key areas for later on. The primary structure can be defined, but bay spacing, connection detailing, and localized strengthening allow for future modifications in high-probability areas. Both site and utility planning should anticipate growth by incorporating spare conduits, ductbanks, and accessible tie-in points that enable expansion without disruption. These decisions do not require overdesign everywhere; rather, they target allowances in locations where change is most likely.
- At the systems level, adaptability should be a guiding principle during planning and design.
- Regularized structural grids can support multiple program types.
- Mechanical systems can include provisions for future connections, isolation, and incremental capacity increases.
- Electrical infrastructure can be planned with space for expansion and clear distribution pathways.
- IT/OT systems can incorporate redundant routes and scalable spaces to accommodate growth in technology demands.
- Fire protection systems can be zoned and configured to allow extensions without widespread disruption.

Incorporating flexibility into structural systems, utilities, and building infrastructure can help facilities embrace future modifications easily.
Deliberate and Functional
A project’s long-term value is defined less by how precisely it meets today’s requirements and more by how effectively it can respond to what comes next. In practice, this is not easy. Often, project teams are under pressure to solve immediate needs quickly and efficiently, which can pull focus toward short-term decisions that satisfy current requirements but limit flexibility.
Designing for adaptability means deliberately carving out space in the process to consider what could change. Structural grids should accommodate future loading conditions. Utility infrastructure should allow expansion without disruption. Building zones should support reuse as operations evolve. When these considerations are addressed, facilities become platforms that can absorb change rather than resist it—allowing new technologies to be integrated and spaces to be reconfigured without major reconstruction work.
Design also must account for the speed at which future mission demands will shift. Requirements will continue to evolve faster than traditional project timelines—and that means facilities need to keep pace. Planning for phased upgrades, reducing downtime during modifications, and enabling the rapid deployment of new systems all contribute to long-term performance. A focus on adaptability during design positions facilities to remain relevant and functional over time, while maintaining continuity of the mission.
Speeding Up Delivery
There are three main reasons that accelerated schedules are becoming more typical within the defense sector.
First, mission readiness. Military facilities directly support mission-critical operations. Delays can impact training, deployment, or national security objectives. Accelerated schedules enable the faster delivery of operational capability, ultimately making sure warfighters have the infrastructure they need.
Second, defense projects are tied to strict congressional appropriations with defined obligation and expenditure timelines. Accelerating the schedule helps funds be obligated and executed within the fiscal window, reducing the risk of reprogramming or loss of funding.
Third, most projects occur within fully operational installations. Implementing compressed schedules can reduce the duration of construction impacts such as access restrictions, noise, and safety risks—with minimal interference to operations. Accelerated execution minimizes downtime, temporary relocations, and disruptions to personnel and mission-critical functions.
Adam Skwirsk, AIA, M.SAME, is Associate Principal, AECOM; adam.skwirsk@aecom.com.
Published in the November-December 2026 issue of The Military Engineer

Check Out Related Articles From TME
-
Innovative PFAS Remediation at Camp Grayling
For project stakeholders and remediation managers confronted with PFAS, Regenesis demonstrates the efficacy of using Regenesis’ PlumeStop® colloidal activated carbon (CAC) at Camp Grayling, Michigan. -
A Standardized Approach to Aircraft Fire Training Infrastructure
To support enterprise-wide airmen readiness, the U.S. Air Force is modernizing its standard design for aircraft fire training facilities—introducing digital controls, dual-fuel systems, and PFAS-conscious infrastructure. -
Delivering Energetic Materials Manufacturing Facilities
Designing and constructing facilities that manufacture, process, handle, or store explosives and energetic materials present some of the most challenging defense projects—requiring technical experience, strict safety protocols, and a comprehensive understanding of regulatory frameworks. -
Forging Tradition and Innovation: A New Design Standard at Camp Lejeune
The II MEF Headquarters at Camp Lejeune blends Georgian Revival architecture with modern sustainability—delivering durability, efficiency, and precision that meets contemporary functional requirements while honoring heritage. -
Balancing Efficiency and Fiscal Responsibility
The continuing contracts clause offers the U.S. Army Corps of Engineers a way to improve project delivery and enhance fiscal responsibility by aligning funding with project execution. -
Next Steps for Digital Twin Development
U.S. Forces Japan is laying the groundwork for future integration of digital twin technology in order to validate and collect data that will offer comprehensive insights into utility conditions at installations and enhance overall decision-making, efficiency, and resilience.