Rebuilding the Pentagon After 9/11, and Beyond
By Scott Winkler and Curt Eisenhower
Following the terrorist attacks of Sept. 11, 2001, a previously planned renovation for the Pentagon took on new scope, urgency, and national importance, with an integrated project team pivoting to complete the rebuild within a year.

In rebuilding the Pentagon after the terrorist attacks of Sept. 11, 2001, integrated project teams were empowered to make decisions and leverage close partnerships in order to accelerate delivery while continuing to maintain exceptionally high standards for security at the site. Photos courtesy Southland Industries.
In 2001, the Pentagon needed more than routine maintenance. After 60 years of operation, the installation was in need of significant, multi-year renovations. The investment program would implement infrastructure that would last for 50 years, with the work onsite coordinated to minimize impact on tenants.
The overall program, which included a focused renovation of Wedges 2-5, was scoped and planned before the tragic events of Sept. 11. After the terrorist attacks, what would have been an expansive but straightforward renovation turned into an urgent rebuild, in the throes of a national mourning. At a time of heightened security, construction had to be completed on a compressed schedule and a higher standard of protection, and all without interrupting the mission-essential work at America’s defense headquarters.
Initial Renovation Plans
Before renovation of Wedges 2-5 got underway, upgrades on Wedge 1 of the Pentagon were nearing completion in September 2001, having been delivered through design-bid-build under roughly 3,500 pages of technical specification. This phase of the program also presented a good time to review the overall building renovation schedule and budget. The design included less than 8-ft ceiling plenums running through occupied space and windows partially blocked at the perimeter, limiting sunlight. After a detailed review, the Pentagon Renovation Office concluded that the allocated budget would run short of what was needed.
When it came time to modernize the remaining wedges, the renovation office embraced a major shift in typical government contracting. It created a single design-build package, where detailed specifications were replaced with a performance specification. Room types were listed with specific design conditions, including temperature, relative humidity, and space plug loads. Energy budgets were set per wedge, with an award fee tied to performance. Water-source heat pumps were excluded. The Pentagon requested that systems work across a 50-year horizon; this stipulation pushed bidders to include lifecycle cost analysis rather than first-cost comparison.
Southland Industries was awarded the contract late that summer—after diverging from the original Wedge 1 design to include higher ceilings, no expensive bulkheading at windows, indirect light in exterior high bay areas, and energy saving exterior zone lighting controls. The team developed a concept based on 20×20 zones and rigid but flexible furniture plans. These designs allowed for structural savings and short interval production schedules, by breaking down each team’s construction time into one week per bar. This incentivized a process that enabled delivery on budget and allowed for a predictable turnover of spaces.
Rising From the Ashes
It was 25 years ago that the planned renovation for the Pentagon changed in an instant.
We were two miles from the Pentagon when the plane flew past on Sept. 11, 2001, in a kickoff meeting for a project that was about to be forever altered and suddenly become a matter of national security. Within a day, while the nation stood in shock, a team was created for a highly visible mission: rebuild the damaged section within a year.
A countdown clock stood in front of the field trailers, too large to miss. But it never read as pressure. Everyone on that site understood what the date meant, and the clock became something the work moved toward rather than against.
From that moment on, everyone was committed to the work—both in getting it done quickly and completing it the right way.
Union tradespeople worked around the clock, proud to support a project that stood for something larger than the building itself.
Our team met daily to make critical decisions.
Engineers who were there still call it the proudest work of their careers. Being asked to help at that moment meant something, but getting it right meant more.
The rebuild effort was named Project Phoenix, for the bird that rises from its own ashes. A quarter-century later, the name still fits—and the impact of the work endures.
Post-Attack Changes
After receiving the official notice of award just before Sept. 11, the design-build kickoff meeting was getting underway about 2-mi away from the Pentagon when the American Airlines Flight 77 approached, tragedy moments away.
Sections of Wedges 1 and 2 were damaged. The team responsible for Wedge 1 returned to fix what they could. Wedge 2 became a change order against a contract that had just been signed. The revised language, including new requirements to reoccupy within one year, with a countdown clock posted on site.
Clearing debris from the crash site took about a month, after which concrete was poured seven days a week. The structural engineer needed sleeve locations, penetrations, and equipment weights before a mechanical design existed. To accomplish this, an integrated project team formed, and change requests carried a 24-hour decision requirement, with tiered thresholds so the smallest changes could be approved on the spot. These actions allowed for essential flexibility. When demolition finished ahead of schedule and the outer ring design was not yet ready, the team reversed the planned construction sequence and started from the inner ring.
The technical requirements for the project also changed following the terrorist attacks. The rebuilt section picked up new building codes, which enhanced safety upgrades that were included in the original plan. Additional changes included new mechanical and plumbing systems meant to meet any perceived potential future threats.
The renovation at the Pentagon took on an influential position in the nation’s recovery. In the days following the attacks, Congress authorized emergency funding, and the Department of Defense moved the project to the top of the priority list. The original renovation end date, however, did not move, which meant that the Pentagon Renovation Office’s team-oriented leadership was critical to success.

A fan-powered induction air distribution system, which was built on then-innovative technology, reduced above-ceiling infrastructure requirements while meeting the Pentagon’s cooling needs.
System Without Precedent
The real engineering challenge with rebuilding sections of the Pentagon came down to using sensible cooling systems in what is a high-humidity region of the country. The Pentagon Renovation Office needed a fix for condensation, and the project owner required drains at every unit for it to be accepted. To account for this, the mechanical team evaluated 10 distribution systems to find a solution: five deemed conventional and five considered innovative at the time.
The team found that conventional duct-based air delivery did not fit the available plenum, and water-source heat pumps were off the table. Additionally, the design intent was to increase ceiling heights, not constrain them. With these necessities considered, a fan-powered induction unit arrangement was chosen as the best option. With central fans supplying outdoor air, terminal units were able to hold a cooling coil, an electronically commutated motor, and a pressure-independent air valve to deliver a constant volume of conditioned outdoor air. From there, outdoor air was cooled to a 48-°F design dewpoint and delivered near 52-°F after fan reheat. At the terminal, outdoor air and induced room air would pass across a coil supplied with chilled water that was warm enough to avoid condensation in the occupied space. Exterior zones were then heated by fin-tube hot water radiation with controls integrated into the terminal.
Taking this approach had an important impact on ceiling heights as well. For a branch delivering 10-T, a variable-air-volume system needs roughly a 20-in duct. The same capacity through a fan-powered induction unit needs only a 10-in duct for outdoor air and two 1.5-in chilled water pipes (allowing above-ceiling space requirements to decrease by 23-in). Additionally, the architects moved the plenums over corridors and core spaces and left the full 11-ft of exterior wall exposed.
Implementing this system did not come with a design manual—and there was no historical performance data to design from. The fan-powered induction system had only been used once before in a building of about 20,000-ft²; at the Pentagon, it would be applied across millions of square feet of the largest office building in the world.
The concerns were addressed by partnering with a manufacturer whose research and development laboratory in Texas could build and test a prototype. Inside Wedge 2, the team built a 10,000-ft² mockup, complete with architectural finishes and fully operating mechanical systems. About 30 government engineers were brought to commercial buildings in the region that were already running floor-mounted induction systems in order to put their questions directly to the facility operators who maintained them.
The mockup immediately proved dividends. First, it solved a service-access problem: a component that needed 3-ft of clear working space had nowhere near it, so the team reoriented the unit to open and be serviced from below through hinged panels. It also reversed an already-made procurement decision, once a competing manufacturer’s unit proved to perform better under the same conditions.
On the job site, adhering to sound calculations is not always enough. Key decisions were made by those who had experience maintaining the facility for years. Giving them the chance to test the approach allowed for a more effective long-term solution.
Design, Build, Repeat
Once a satisfactory plan had been established, an integrated project team met every morning for a year—first outdoors near the helipad and later in a co-located trailer complex that held every organization with a decision to make.
The reason this was successful was not due to proximity, but rather the authority those in the room had to decide without delay. In practice, this meant actions could be taken even if the design was not fully completed, lowering the risk of delays. As a result of this partnership, re-occupancy of the building occurred one week before the 12-month mandate and came in roughly $200 million under budget. There were zero recordable incidents, and the comprehensive Wedges 2-5 renovation was completed ahead of schedule.
25 Years of Innovation
In 2001, the coordination between teams was two-dimensional because 3D drafting tools were not mainstream at the time. The Pentagon Renovation Office had specified a software package predominately used for civil and process piping. In 2026, the facility could readily be scanned in a 3D model for backgrounds and then modeled to within 1/2-in accuracy.
Additionally, the terminal units used in the system then are no longer unusual. Most manufacturers of fan-powered VAV terminals now catalog a version, generally called a fan-powered terminal unit with a sensible coil. Roughly 20,000 units were installed in the Pentagon as part of the renovation process, with the units set in Wedge 2 still in service today a quarter-century later.
Finding New Solutions
The planning and engineering that went into this historic project may have been 25 years ago, but the issues addressed still appear in project delivery today. Occupied buildings still need modernizing. Aging structures still refuse conventional systems. Owners still have to decide whether to accept new solutions, based on prototypes, models, and collaborative understanding of how to solve the issues at hand.
An unproven system is sometimes the correct answer, but only where the verification burden is taken on at the front end rather than argued afterward. This is why it is important to take the time to get it right by building the prototype and mockup—and by bringing project owners into the testing process so they can see the results.
With this groundwork and understanding built, performance specifications can produce engineering solutions that more prescriptive specifications rule out.
Scott Winkler is Senior Vice President of Engineering, and Curt Eisenhower is Principal Engineer, Southland Industries. They can be reached at swinkler@southlandind.com; and ceisenhower@southlandind.com.
Published in the November-December 2026 issue of The Military Engineer

Check Out Related Articles From TME
-
Innovative PFAS Remediation at Camp Grayling
For project stakeholders and remediation managers confronted with PFAS, Regenesis demonstrates the efficacy of using Regenesis’ PlumeStop® colloidal activated carbon (CAC) at Camp Grayling, Michigan. -
A Standardized Approach to Aircraft Fire Training Infrastructure
To support enterprise-wide airmen readiness, the U.S. Air Force is modernizing its standard design for aircraft fire training facilities—introducing digital controls, dual-fuel systems, and PFAS-conscious infrastructure. -
Delivering Energetic Materials Manufacturing Facilities
Designing and constructing facilities that manufacture, process, handle, or store explosives and energetic materials present some of the most challenging defense projects—requiring technical experience, strict safety protocols, and a comprehensive understanding of regulatory frameworks. -
Forging Tradition and Innovation: A New Design Standard at Camp Lejeune
The II MEF Headquarters at Camp Lejeune blends Georgian Revival architecture with modern sustainability—delivering durability, efficiency, and precision that meets contemporary functional requirements while honoring heritage. -
Balancing Efficiency and Fiscal Responsibility
The continuing contracts clause offers the U.S. Army Corps of Engineers a way to improve project delivery and enhance fiscal responsibility by aligning funding with project execution. -
Next Steps for Digital Twin Development
U.S. Forces Japan is laying the groundwork for future integration of digital twin technology in order to validate and collect data that will offer comprehensive insights into utility conditions at installations and enhance overall decision-making, efficiency, and resilience.