Coordinating Modular System Delivery for a New Military Hospital
By Cindy Elkin, IIDA, CHID, EDAC, NCIDQ, RID, Tim Williams, AIA,LEED AP, M.SAME, Donald Sellers, RCDD, LEED AP, and Mark Troast, CPD, LEED AP, ASSE 6060
A project to deliver modular systems as part of the General Leonard Wood Community Hospital assigned coordination ownership based on level of utility integration to increase accountability and improve infrastructure delivery.

The General Leonard Wood Community Hospital demonstrates how modular systems can be evaluated by their level of utility integration to improve accountability and project delivery. Photos by Chad Baumer. Photography and Bob Greenspan Photography.
When a modular furniture system carries power, data, plumbing, medical gas, or other building services, it stops being furniture and becomes part of the building’s critical infrastructure. That shift also changes how the inventory should be coordinated—and, importantly, who should own that coordination.
In military healthcare facilities, many government-furnished modular systems are technically removable, yet they tie into fixed components that are designed, installed, tested, and commissioned by others in support of patient care. From office space to nurse stations, laboratories, and pharmacies, every utility connection creates another coordination point between the building and the modular system.
The recently completed General Leonard Wood Community Hospital at Fort Leonard Wood, Mo., illustrates how quickly that complexity can grow. Across the 452,979-ft² hospital and clinic, which replaced the hospital center that had been built 60 years ago, modular office workstations, nurse stations, pharmacy, and laboratory spaces serve a wide range of care environments, each with different utility requirements and supporting responsibilities.
Rather than revealing a single solution, however, the integration produced a practical framework for evaluating modular systems by their level of integration with the building infrastructure. That framework can help other project teams assign responsibility, align procurement strategy, and reduce costly field conflicts before construction begins.
Furnishing Construction
How new military healthcare facilities are typically delivered encounters many unique challenges facing what is already a specialized field of design and construction.
In most projects, the building is constructed under its own contract whereas government-furnished equipment, furnishings, and modular systems are provided through a separate contract for Initial Outfitting and Transition (IO&T). The construction contractor is responsible for bringing utilities to the modular system, while the IO&T contractor installs the furniture and equipment after construction is substantially complete. This traditional division of responsibility works well for components requiring little more than a standard electrical receptacle. It becomes far more complicated when modular systems require multiple building utilities.
Rather than treating every modular system alike, the project team determined where responsibility transferred from the building infrastructure to the modular system. The answer depended on the number and type of utility connections each modular system required.
Defining Responsibility
As Designer of Record for the General Leonard Wood Community Hospital, RLF worked under contract to the design-build contractor rather than directly with the Kansas City District of the U.S. Army Corps of Engineers. This contractual structure required the modular system coordination to be managed through the contractor, which demanded disciplined communication and close collaboration among all the partners.
In other examples within military healthcare projects, without clearly defined ownership, coordination problems can often surface after building systems have been installed. Relocating rough-ins, rerouting utilities, or returning contractors to complete unfinished work can add unnecessary cost and delay.
The overriding lesson learned is in determining where responsibility for each building-to-furniture connection belongs.

As modular systems become more deeply integrated with building utilities, assigning clear ownership of connections can reduce installation conflicts and costly modifications. Illustrations by Jocelynn White, Studio Fritz/RLF.
Evaluating Integrations
A key takeaway on the General Leonard Wood Hospital is that not every modular system should be coordinated the same way. The appropriate procurement and installation strategy depends on how deeply the system integrates with the building’s infrastructure. Rather than treating every modular system alike, the project team determined where responsibility transferred from the building infrastructure to the modular system. The answer depended on the number and type of utility connections each modular system required. To define those responsibilities, the team identified who would furnish devices, route utilities to the modular system, complete final connections, and perform testing and commissioning.
As the number and complexity of those interfaces increased, so did the need for clear ownership. Those differences shaped how each system was coordinated.
The project team identified four levels of coordination complexity, each driven by the degree to which the modular system integrated with the building’s infrastructure.
Office Workstations. The traditional office workstation represented the simplest condition. The Army’s standard panel systems relied on nearby wall outlets for power and data, which allowed equipment to plug directly into the building infrastructure. Because the utilities terminated at the wall, coordination between the building and the furniture remained relatively straightforward.
Ganged Workstations. The team encountered another level of complexity with open office workstations. Instead of receiving utilities directly from adjacent walls, these workstation clusters required power and data to be routed from floor-mounted connections through the furniture system to serve multiple workstations.
The design-build contractor provided 20-ft power and data whips at each cluster. After the electrical subcontractor completed the rough-in, the whips were left coiled at the floor for the furniture installer to route through the modular system to outlets embedded within the workstation run. That arrangement required clear coordination between the electrical subcontractor and the furniture installer.
Embedded devices created another ownership question. The furniture manufacturer provided knockouts for receptacles and data ports, but not the devices themselves; this required the project team to define who would furnish, install, and connect those components before installation began.
Nurse Stations. The nurse stations marked the point where modular furniture became building infrastructure. Unlike office workstations, nurse stations required both normal electricity and emergency power distributed through separate raceways, along with data and a range of department-specific low-voltage systems, including nurse call, patient monitoring, and security. Because these systems needed multiple building utilities to pass through the modular furniture, dividing responsibility between the design-build contractor and the IO&T contractor introduced coordination risk.
To simplify the process, the nurse stations were procured through the design-build contractor under a separate Contract Line Item Number. This gave a single entity responsibility for coordinating utility rough-ins, furniture installation, final electrical and low-voltage connections, testing, and commissioning.
The nurse stations marked the point where modular furniture became building infrastructure. Unlike office workstations, nurse stations required both normal electricity and emergency power distributed through separate raceways, along with data and a range of department-specific low-voltage systems, including nurse call, patient monitoring, and security.
The same principle applied to information and communications technology systems. Continuous horizontal cabling, testing, and certification were significantly easier to coordinate when the building systems and modular furniture were installed under the same contract rather than through separate procurements. This was true for hardwired utility connections as well. Floor penetrations had to align with the nurse station’s utility entry points so that power, data, and other building services could be routed through the modular system as intended. When they did not align, exposed wiring, installation conflicts, and field modifications could result.
Laboratory and Pharmacy Workstations. The highest level of utility integration was reserved for laboratory and pharmacy workstations. These systems incorporated combinations of power, data, plumbing, gases, deionized water, and other specialized utilities within the modular framework. The utility rough-ins varied by location, while the modular framing provided separate pathways for power, plumbing, and other utility services.
Utilities originated from multiple sources beyond the furniture manufacturer. The countertops were provided as part of the workstation; sinks, plumbing fixtures, electrical devices, communications outlets, and utility connections all were coordination by various trades through the design-build contractor.
Shutoff valves at the rough-in connections allowed the IO&T contractor to certify the medical and laboratory gas systems downstream without recertifying the piping network upstream of the valves. That approach simplified certification while preserving the integrity of the installed building infrastructure.
Although these modular systems were not reassigned by Contract Line Item Number as the nurse stations were, the team concluded that future projects would benefit from coordinating them through the design-build contractor in order to ensure that infrastructure and furniture functioned in unison.
As modular and prefabricated systems continue to evolve, more components will function as both furniture and infrastructure. Delivering them together requires recognizing that distinction early enough to align procurement, installation, and utility coordination with the proper level of integration each system demands.
Ensuring Alignment
The lessons from the General Leonard Wood Community Hospital extend beyond a single military healthcare project. As modular and prefabricated systems continue to evolve, more components will function as furniture and infrastructure. Delivering them together requires recognizing that distinction early enough to align procurement, installation, and utility coordination with the proper level of integration each system demands. Modular systems are often procured years after design, when technology, codes, product availability, and costs may have changed.
Additionally, the earlier that teams recognize when a modular system has become part of the building infrastructure, the sooner they can determine which party should own its coordination. That crucial decision can reduce field-level conflicts, simplify project delivery, and help integrated building systems perform as intended from the first day the facility opens.
Procurement to Ownership
The General Leonard Wood Community Hospital demonstrated that procurement strategy is fundamentally a coordination decision. The more deeply a modular system integrates with the building infrastructure, the greater the benefit of assigning coordination to a single entity.
Without clearly defined responsibility, even routine utility connections can become sources of delay, rework, and added cost. Because the contractor’s responsibility ends at facility turnover, work tying modular systems to building services must be assigned before that handoff. Otherwise, resolving a missed connection may require bringing contractors back into a completed facility. A misaligned plumbing or medical gas rough-in, for example, may require finished walls or floors to be opened so piping can be rerouted to align with the installed modular system. Beyond the immediate construction cost, those changes can affect schedules, inspections, and finish continuity.
By assigning responsibility levels according to each system’s level of integration, the project team established clear accountability before construction work began. That approach reduced coordination challenges during the installation period and helped ensure that increasingly complex modular systems functioned as intended once they became fully part of the completed facility.
Cindy Elkin, IIDA, CHID, EDAC, NCIDQ, RID, is Senior Interior Designer, Tim Williams, AIA, LEED AP, M.SAME, is Senior Project Manager, Donald Sellers, RCDD, LEED AP, is Discipline Director – Low Voltage, and Mark Troast, CPD, LEED AP, ASSE 6060, is Senior Plumbing & Fire Suppression Designer, RLF Architecture + Engineering + Interiors Inc. They can be reached at cindy_elkin@rlfae.com; tim_williams@rlfae.com; donald_sellers@rlfae.com; and mark_troast@rlfae.com.
Published in the November-December 2026 issue of The Military Engineer

Check Out Related Articles From TME
-
Innovative PFAS Remediation at Camp Grayling
For project stakeholders and remediation managers confronted with PFAS, Regenesis demonstrates the efficacy of using Regenesis’ PlumeStop® colloidal activated carbon (CAC) at Camp Grayling, Michigan. -
A Standardized Approach to Aircraft Fire Training Infrastructure
To support enterprise-wide airmen readiness, the U.S. Air Force is modernizing its standard design for aircraft fire training facilities—introducing digital controls, dual-fuel systems, and PFAS-conscious infrastructure. -
Delivering Energetic Materials Manufacturing Facilities
Designing and constructing facilities that manufacture, process, handle, or store explosives and energetic materials present some of the most challenging defense projects—requiring technical experience, strict safety protocols, and a comprehensive understanding of regulatory frameworks. -
Forging Tradition and Innovation: A New Design Standard at Camp Lejeune
The II MEF Headquarters at Camp Lejeune blends Georgian Revival architecture with modern sustainability—delivering durability, efficiency, and precision that meets contemporary functional requirements while honoring heritage. -
Balancing Efficiency and Fiscal Responsibility
The continuing contracts clause offers the U.S. Army Corps of Engineers a way to improve project delivery and enhance fiscal responsibility by aligning funding with project execution. -
Next Steps for Digital Twin Development
U.S. Forces Japan is laying the groundwork for future integration of digital twin technology in order to validate and collect data that will offer comprehensive insights into utility conditions at installations and enhance overall decision-making, efficiency, and resilience.