Preserving Legacies While Meeting the Mission



By Steven Blashfield, AIA, LEED AP, M.SAME 

Through detailed research, evaluation, planning, and execution, historic military facilities can be adapted to meet today’s evolving needs while also preserving the architectural character and heritage that define them.

A rehabilitation project at Fort Monroe demonstrates how historic military structures can be adapted for new uses when preservation goals are aligned with operational and programmatic requirements early in design. Photos by Virginia Hamrick Photography.

The challenge of managing older structures on military installations has become more prominent in recent years. A 2022 report from the Government Accountability Office found that nearly 30 percent of the Defense Department’s 550,000 structures have exceeded their lifespan. Many are no longer suitable for their intended purpose.

The process of preserving historic structures can be complicated and frustrating when review bodies establish findings that prevent replacements or adaptations. At the same time, many of the unique historic structures on military bases contain features and details that would be nearly impossible to recreate today. Because of the dichotomy between the process and the review requirements, contracting officers are now insisting that IDIQs, MATOCs, and individual project work orders include professionals with historic preservation expertise. 

The need to repurpose historic structures will only continue.  With improved guidance and understanding, the process of rehabilitation can become more understandable, and even desirable as an approach.

Conducting Detailed Research

Undertaking proper, detailed research is the basis for success of any project. This is especially true for a rehabilitation or adaptive reuse involving historic structures. It is critical to allow time for detailed site reviews, as well as to understand the history and evolution of a building in order to evaluate its potential for preservation and adaptation. 

Advanced technology now allows buildings to be 3D digitally laser scanned and modeled. This technique has significantly advanced opportunities for documenting and evaluating the condition of these structures and determine key deficiencies. Features such as sloping floors and sagging beams, which may be less visible, become more evident in digital analysis—as do other issues that previously were only discovered as unforeseen conditions during the construction phase. 

It is also crucial to analyze historic documents and building plans early in the design process. Many installations have archived plans and details about previous renovations or changes made to the buildings. At Norfolk Naval Shipyard, Va. (first established back in 1767), the cultural resources staff is a central source for information on historic properties and has maintained significant archives that can be utilized during the research phase. Tapping into those records and base documents is a source of valuable material and guidance. 

Rehabilitation projects involving historic buildings, especially on federal properties, require the application of the Secretary of Interior Standards for Historic Preservation. This metric is what state historic preservation offices use when considering the impact and appropriateness of proposed changes as well as compliance with Section 106. The process of documentation helps the design team provide a guide to interventions and supports the justification of the design. Providing reviewers with an understanding of the history of a structure improves the review process.  

Documenting changes made to a building over time facilitates the development of integrity maps. These help identify the concentration of the original and historic fabric of buildings. For example, on a recent rehabilitation at Norfolk Naval Shipyard involving extensive renovations to an 1860s building originally built as a warehouse, the project team completed a detailed survey of the original windows and mapped the façades to determine the extent of repairs needed. Understanding that the State Historic Preservation Office wanted historic windows to remain in place, the team coordinated a series of details that allowed original wood windows to be kept while reinforcing the openings to meet new blast resistance criteria. This evaluation process did add some time at the outset. But it also allowed for much more detailed and accurate estimating early in the development phase. This all culminated in less unforeseen contingencies and strong support from reviewers during the historic review process. 


Early investigation of historic documents, researching building evolution, and analyzing existing site conditions provides a strong foundation for evaluating steps in the facility rehabilitation process. 

Building a Shared Plan

Once consensus has been gained on where changes have been made to a building and the extent of those changes over time, areas with limited original elements become prime opportunities to insert new features. These diagrams provide the guideposts to target improvements and adaptations that minimize the loss of historic aspects. 

This process continues as a project team moves to evaluate approaches. Building viability is reviewed on two levels. First, how heavily has the building been modified, and how extensive are those modifications? Second, how does the building need to be renovated to make it useful? 

Many federal buildings and base architecture have undergone extensive modifications. Sometimes these are a series of small-scale changes. Over time, the renovations end up covering over original features. A prime example of this kind of modification history is Building 138 (Wisser Hall) at Fort Monroe, Va. After the installation was closed in 2011 through Base Realignment and Closure and reverted over to the state, the interior of Building 138 was barely recognizable from its original configuration. Formerly serving as the library of the Coast Artillery School, conversions throughout the years had turned the building into staff offices with a maze of wires, conduits, and subdividing partitions. The facility was slated to become a visitor center at the former base, now a national monument site. Through investigation and analysis, a number of features were identified that could be brought back during the rehabilitation project, including decorative terrazzo floors, a central skylight, and elaborate millwork. 

The process of analysis combines an evaluation of the data collected in the research phase with a thorough understanding of the new programmatic needs for a facility. Sometimes, however, the process simply seeks to determine if a facility is adequate for its intended use.

At Norfolk Naval Shipyard, multiple structures were evaluated to determine if they could be upgraded to meet functional working needs along with contemporary force protection requirements. Not all outcomes have been the same; recommendations at times do include demolition. It is often useful to bring these consulting evaluation services under a separate task order before the larger projects are fully developed, to help guide resource allocation. 

Buildings with higher degrees of historic integrity and unique or high-quality features may merit additional effort that would not normally be applied to more utilitarian structures. For example, an 1890s-era barracks built for Marines, featuring a dramatic Romanesque style brick façade, including a series of exterior porches, is a signature building to the identity of Norfolk Naval Shipyard. When upgrading that structure, extra time and care were applied to evaluate its reinforcement systems to harden the building for progressive collapse while not losing the visual integrity of the original façade. 

Transformation Begins

Once the research and analysis steps are complete, discussions about the building’s transformation can begin. 

For the Fort Monroe Visitor Center, expectations for the adaptation of this 1909 Beaux-Arts style building and the understanding of what could be achieved within the historic review process were limited. The solution proposed, which included removing and realigning two floors in the rear ell and construction of two sympathetic additions to expand functionality and accessibility, were beyond the expectations of what could be achieved when the site was initially identified for adaptation. Now jointly operated by the Fort Monroe Authority and the National Park Service, the center sees more than 100,000 visitors through its doors annually. 

With the vast number of existing structures on federal installations, many decades-old, extensive work remains to continue to maintain and upgrade these facilities to current needs. However, there are numerous exceptional buildings in these spaces that would be difficult to create today. Adapting them allows a path to capitalize on existing assets, while retaining a connection to the long and storied history of our military and the men and women who serve our nation. 

Steven Blashfield, AIA, LEED AP, M.SAME, is Senior Principal and Director of the Cultural Studio, Glavé & Holmes Architecture; sblashfield@glaveandholmes.com.


The Military Engineer archives