Renewing Water and Sewer Systems at Fort Detrick
By Eric Stahl, P.E., LEED AP, CQM-C , M.SAME, Emily Durkin, CQM-C, and Susan Knox
A pair of parallel repair and renewal projects at Fort Detrick utilized a self-perform integrated design-build process to modernize aging potable water and sanitary sewer systems while maintaining continuous operations.

An integrated design-build approach enabled Fort Detrick to modernize aging water, wastewater, and fire protection infrastructure while maintaining utility services during the projects. Photos courtesy Weston Solutions.
Located west of Baltimore in Frederick County, Md., Fort Detrick supports military readiness, biodefense research, public health, and national security, hosting five cabinet-level departments, including the Department of War, Department of Veterans Affairs, Department of Agriculture, Department of Homeland Security, and Department of Health & Human Services. The installation also houses the National Interagency Biodefense Campus, which includes the U.S. Army Medical Research Institute of Infectious Diseases and other agency Biosafety Levels 3 and 4 laboratories.
An influx of significant mission and facilities expansion over the past two decades has created a demand for infrastructure renewal at the base. In 2019, sanitary sewer repairs were already underway when a second project was initiated to replace deteriorated potable water and fire protection infrastructure. For nearly four years, both efforts advanced across the same road networks, utility corridors, secure areas, and administrative, research, and housing areas. The Army’s Engineering & Support Center, Huntsville, in conjunction with the Baltimore District of the Army Corps of Engineers (USACE), had awarded the design-build task orders under the Facility Repair and Renewal Program for a combined $26.7 million.
Throughout the duration of the work, challenges extended beyond replacing old piping systems. Maintaining water, wastewater, fire protection, traffic, security, and tenant access to these mission-critical assets had to remain available during construction. What proved to be the key to keeping the projects moving while minimizing impacts to base operations was an integrated design-build process.
System Improvements
Both the sewer and the water and fire protection systems at Fort Detrick included infrastructure dating to the 1940s. The gravity sanitary sewer mains contained vitrified clay, cast-iron, concrete, asbestos-cement, and polyvinyl chloride pipe. Over time, cracked lines, failing joints, deteriorated manholes, and improper drainage connections allowed groundwater and stormwater to enter the system. The added flow consumed wastewater treatment capacity, increased operation costs, contributed to overflow risk, and limited future mission growth.
The potable water and fire protection network faced different challenges brought on by age. Both cast iron and ductile iron mains had reached the end of their useful service lives. Inadequate burial depths contributed to winter breaks. Internal scale restricted flow. Frequently, tenants received discolored or turbid water. A 2019 study reported that leaks and losses accounted for 31 percent of water use from 2007 through 2012.
Sustaining infrastructure readiness enables mission readiness. The failure of either system could interrupt laboratory operations, constrain firefighting, affect housing and industrial tenants, and compromise environmental compliance. The repair projects had to correct long-term deterioration without creating a disruption in service.
Acquiring Upgrades
Although executed under a traditional design-build process through the Federal Acquisition Regulation, early collaboration with Fort Detrick’s Directorate of Public Works, USACE, and installation stakeholders and tenants aligned planning, design, and construction from the outset. This improved constructability, optimized phasing, and reduced risk within this mission-critical environment. The collaboration provided a common framework for resolving conflicts and coordinating work. Weston Solutions served as design-build contractor for both task orders, integrating self-performed investigation, engineering, design, permitting, waste management, construction, restoration, and commissioning.
Capturing accurate subsurface information is essential, and especially so in an environment with dense infrastructure, undocumented utilities modifications, shallow bedrock, restricted areas, and requirements around Controlled Unclassified Information. The site work at Fort Detrick included location surveys, subsurface utility engineering at Quality Levels A and B, ground-penetrating radar, soft-dig verification, geotechnical testing, hydraulic analysis, and hazardous materials sampling.
For the sewer system, the project team used closed-circuit television inspections, dye testing, flow monitoring, hydraulic assessment, and manhole evaluations to identify needs of the system. For the water system, the investigations included acoustic leak detection, valve assessments, hydraulic modeling, and hydrant flow testing that was coordinated with the Fort Detrick Fire and Emergency Services Division of the Directorate of Emergency Services (DES).
A series of design workshops combined the findings with construction and stakeholder knowledge. The project team evaluated specifications and restoration phasing and prioritization before finalizing designs. That input supported an approach that leveraged trenchless sewer rehabilitation and parallel water main installation where feasible. Constrained segments were planned for existing trench replacement after temporary service and outage requirements were established.
Phasing Operations
The project was divided into controlled work zones in order to limit effects on traffic, housing, tenant access, installation operations, and adjacent projects.
A combination of detailed schedules and three-week look-ahead plans were developed and shared with USACE, the Directorate of Public Works, security personnel, inspectors, tenants, and DES. Most individual water-service connections were completed in less than two hours.
- Temporary systems preserved continuity when the work required more than a brief interruption.
- Sewer measures included flow-through plugs, bypass lines, pumps, and temporary storage tanks.
- Above-ground bypasses were protected from vehicles and pedestrians, while careful detours maintained circulation for traffic.
During the project, weekly meetings and daily communication helped when needing to respond to weather, subsurface conditions, tenant needs, and project conflicts. Crews shifted zones, adjusted sequencing, extended hours, or developed recovery schedules rather than allowing one conflict to stop the broader program.
System Rehabilitation
The sewer project repaired nearly 13,000-linear-ft of sanitary sewer mains, including 10,204-linear-ft of 6-in to 12-in vitrified clay and cast-iron mains. These mains were rehabilitated by using in situ pipe bursting with thermally fused SDR-17 high-density polyethylene pipe. Another 1,114-linear-ft received permanent lining where bursting was not feasible, and 1,523-linear-ft of new polyvinyl chloride sewer mains were installed by open-cut methods to correct capacity, slope, and routing deficiencies.
The team also rehabilitated 154 manholes, installed new precast structures, and constructed a lift station with approximately 150-linear-ft of a new force main. Pumps, controls, and integration-ready telemetry improved reliability and monitoring. Phased bypass pumping was used to maintain wastewater service while each repaired section was connected.
Notably, the work separated stormwater from sanitary systems. Improper drainage connections were redirected. Manholes were lined. Surrounding areas were regraded to keep surface water out and damaged components were either repaired or replaced. Legacy asbestos-containing materials also were abated under the approved plans.
Collectively, these improvements reduced inflow and infiltration, relieved hydraulic demand on the treatment plant, and created capacity for future needs.
Rebuilding Reliability
Alongside the rehabilitation of the sanitary sewer system, the potable water system project renewed 15,000-linear-ft of potable water distribution and fire protection infrastructure. The work included about 13,000-linear-ft of 12-in to 18-in Class 52 ductile iron mains and 2,500-linear-ft of service connections (as well as hydrants, valves, vaults, sub-main system tie-ins, and connections to elevated storage tanks and pump houses).
Where space allowed, crews constructed the new system parallel to the existing mains so that the old network remained in service until testing and cutover were complete. In constrained areas, piping was replaced within the existing alignment using temporary service and planned outages. Fire protection components were coordinated with both USACE and DES. Deteriorated lines were then cut, capped, and abandoned in place.
An acoustic leak-detection network installed during this time also will add long-term value to the system. Sensors in the network can identify potential leak signatures and transmit information through cellular telemetry to a centralized interface, giving the Directorate of Public Works earlier warning of failures. Combined with isolation valves, updated records, and a renewed system capable of supplying approximately 1.4-million-gal per day, the network now supports faster response, proactive maintenance, and greater resiliency.
Supporting the Mission
At closeout, locations of system repairs were incorporated into record drawings and base-wide geographic information system data. This documentation will provide a stronger basis for asset management, maintenance, emergency response, and future planning. In the first year since construction was completed, sewer service orders were reduced by 100 percent. Water main breaks and water quality complaints within the rehabilitated network no longer occur.
While the most visible outcome of the project was a renewed water network and a more capable wastewater collection system, the broader result is a more resilient foundation for the installation’s laboratory research, firefighting, and housing. By utilizing an integrated design and construction approach, field conditions were allowed to shape decisions before they became outages, redesign, or rework.
At an installation where public health and military missions depend on systems that are mostly out of sight, maintaining continuity was just as important as the completed infrastructure. Through early and continuous integration of construction and installation expertise in planning and design, Fort Detrick received both modernized utilities and a coordinated approach that keeps the mission moving.
Maintaining High Standards
The water systems rehabilitation at Fort Detrick recorded zero utility strikes, and both projects completed over 61,000 work-hours without a recordable safety incident. A commitment to health and safety was evident throughout the program.
Before the new water mains entered operation, crews flushed, hydrostatically tested, and disinfected each section. A Maryland-certified laboratory also confirmed acceptable bacteriological level before permanent connections were made.
Finally, the commissioning process for the sewer system included low-pressure air testing, manhole vacuum testing, post construction closed-circuit television inspections, and lift-station startup.
Eric Stahl, P.E., LEED AP, CQM-C, M.SAME, is Vice President, and Emily Durkin, CQM-C, is Marketing Coordinator, Weston Solutions. They can be reached at eric.stahl@westonsolutions.com; and emily.durkin@westonsolutions.com.
Susan Knox is Natural Resource Specialist, Directorate of Public Works, Fort Detrick, Md.; susan.m.knox4.civ@army.mil.
Published in the November-December 2026 issue of The Military Engineer

Check Out Related Articles From TME
-
Innovative PFAS Remediation at Camp Grayling
For project stakeholders and remediation managers confronted with PFAS, Regenesis demonstrates the efficacy of using Regenesis’ PlumeStop® colloidal activated carbon (CAC) at Camp Grayling, Michigan. -
A Standardized Approach to Aircraft Fire Training Infrastructure
To support enterprise-wide airmen readiness, the U.S. Air Force is modernizing its standard design for aircraft fire training facilities—introducing digital controls, dual-fuel systems, and PFAS-conscious infrastructure. -
Delivering Energetic Materials Manufacturing Facilities
Designing and constructing facilities that manufacture, process, handle, or store explosives and energetic materials present some of the most challenging defense projects—requiring technical experience, strict safety protocols, and a comprehensive understanding of regulatory frameworks. -
Forging Tradition and Innovation: A New Design Standard at Camp Lejeune
The II MEF Headquarters at Camp Lejeune blends Georgian Revival architecture with modern sustainability—delivering durability, efficiency, and precision that meets contemporary functional requirements while honoring heritage. -
Balancing Efficiency and Fiscal Responsibility
The continuing contracts clause offers the U.S. Army Corps of Engineers a way to improve project delivery and enhance fiscal responsibility by aligning funding with project execution. -
Next Steps for Digital Twin Development
U.S. Forces Japan is laying the groundwork for future integration of digital twin technology in order to validate and collect data that will offer comprehensive insights into utility conditions at installations and enhance overall decision-making, efficiency, and resilience.